Ministry of Industry and Trade Proposes 5,630 MW Rooftop Solar Targets for 34 Provinces

News Vietnam Editorial team · AI-written, reviewed under our editorial standards · · Reading time 7min read · Views 0 ·
Key — The Ministry of Industry and Trade submitted a draft resolution to the Government on November 20, 2026, assigning 5,630 MW of rooftop solar targets for 34 provinces and cities by the end of 2027.

The Ministry of Industry and Trade submitted a draft resolution to the Government on November 20, 2026, regarding the assignment of targets for self-produced and self-consumed rooftop solar power for 34 provinces and cities. The total projected capacity for rooftop solar power is 5,630 MW. The capacity is divided into two phases: 2,630 MW until the end of March 2027 and 3,000 MW from April to the end of 2027.

How targets are allocated

The allocation of targets is based on electricity load growth, rooftop solar development potential, and grid reception capacity in each locality. Ho Chi Minh City is projected to develop 628 MW of rooftop solar power, with 293.3 MW in the first phase and 334.7 MW in the second phase. Hanoi is projected to develop 510 MW of rooftop solar power, with 238.2 MW in the first phase and 271.8 MW in the second phase.

Other localities with significant targets include Dong Nai (274 MW), Hai Phong (322 MW), Tay Ninh (326.2 MW), and Hung Yen (272 MW). The total estimated investment for 5,630 MW is 67.56 trillion VND, based on an installation cost of 12 million VND/kW, excluding battery energy storage systems (BESS).

How the funding works

The funding sources are social mobilization, state budget, and corporate finance, with household and business installations being voluntary. As of the submission date, only 5 out of 34 localities have issued support policies for household rooftop solar power. The Ministry of Industry and Trade requested that local People's Committees urgently develop and issue support policies by December 2026.

Why this matters

The Ministry of Industry and Trade stated that the allocation of targets is based on electricity load growth, rooftop solar development potential, and grid reception capacity in each locality. The Ministry of Industry and Trade noted that the development of self-produced and self-consumed rooftop solar power, combined with energy storage systems, is a solution to increase local power autonomy, reduce supply pressure, and limit long-distance transmission needs.

The Ministry of Industry and Trade stated that the goal of this model aligns with the adjusted Power Development Plan 8, which aims for 50% of office buildings and 50% of households to use self-produced and self-consumed rooftop solar power by 2030.

Glossary

  • VND — The total estimated investment for 5,630 MW is 67.56 trillion VND, based on an installation cost of 12 million VND/kW, excluding battery energy storage systems (BESS).
  • BESS — The term refers to battery energy storage systems. The excerpt notes that the total estimated investment for 5,630 MW is 67.56 trillion VND, based on an installation cost of 12 million VND/kW, excluding battery energy storage systems (BESS).
  • Power Development Plan 8 — The term refers to the adjusted Power Development Plan 8. The excerpt states that the goal of this model aligns with the adjusted Power Development Plan 8, which aims for 50% of office buildings and 50% of households to use self-produced and self-consumed rooftop solar power by 2030.

This article was written with AI assistance from multiple news reports and is reviewed by our editors under our editorial principles. Editorial Standards · Tips & Contact

How did you like this post?

Comments 0

Be the first to comment

Contact us

← News Vietnam Home
News Vietnam Get new posts by emailSubscribe to receive new content via email. Unsubscribe anytime.
Was this helpful?Share it with friends & social