Automated welding machine deployed to accelerate Phu Quoc Light Rail Transit construction
A 33-ton automated rail welding machine has been deployed at the Phu Quoc Light Rail Transit (LRT) construction site to accelerate progress for the 2027 APEC Summit. The machine, which features a yellow body and an orange cabin, utilizes electric flash butt welding technology to join rails directly on-site. This deployment is part of an effort to meet deadlines for the upcoming summit, with the rail section expected to be completed by March 2027.
Technological advancements in rail construction
The new automated equipment offers significant productivity gains over traditional methods. According to Nguyen Huy Thanh, a representative of the rail welding contractor, "The use of this mobile automated equipment for the first time on the Phu Quoc LRT marks a technological advancement for Vietnamese workers." Nguyen Huy Thanh also noted that "Traditional thermite welding is much less productive than the new automated method."
The automated process is highly efficient, requiring approximately 3 to 4 minutes to complete a single joint. Under favorable conditions, the machine can weld between 250 and 300 meters of single rail per day, which is equivalent to more than 20 joints. The machine requires a minimum of three people to operate. The equipment was imported from a manufacturer ranked among the top five globally in railway construction equipment.
Project scope and investment
The Phu Quoc LRT is a 17.59 km project that includes six stations. It is designed to connect Phu Quoc International Airport with the APEC Convention and Exhibition Center and the South Island area. The project is being implemented under a Public-Private Partnership (PPP) model via a Build-Operate-Transfer (BOT) contract. The total investment for the project is nearly VND 9,000 trillion, with state capital accounting for 70% and Sun Group contributing 30%.
According to reports from Tiền Phong, the project site currently has approximately 1,300 engineers and workers. The heavy construction phase, including piles for bridges and tunnels, is complete, and the tunnel structure from DT.975 to the airport is finished. As of the end of October, more than 11/35 km of rail had been installed.
Timeline and future operations
The project was officially launched in December 2025. Rail track installation began on November 5, 2026, and more than 1 km of welding had been completed by mid-November 2026. The LRT is scheduled for completion in the second quarter of 2027, with trial runs planned for July 2027. Commercial operation is expected to start in November 2027 to coincide with the APEC Summit.
The LRT is expected to have a maximum speed of 100 km/h, with an estimated travel time of 18 to 20 minutes between the airport and the APEC center. The initial phase of the project is expected to operate between 6 and 10 trains, each with three carriages. This would allow for a maximum capacity of 14 trains and 4,500 passengers per hour, according to Tiền Phong.
Glossary
- Phu Quoc — Phu Quoc is a location in An Giang, Vietnam. It is the site of the Phu Quoc Light Rail Transit (LRT) construction project.
- VND — VND is a unit of currency. It is used in financial transactions, such as the investment for the Phu Quoc LRT project.
- Sun Group — Sun Group is an entity that is contributing 30% to the investment for the Phu Quoc LRT project.
- thermite welding — Thermite welding is a manual process used to repair or splice together existing continuous welded rail segments. This process requires a reaction crucible and a form to contain the molten iron.
This article was written with AI assistance from multiple news reports and is reviewed by our editors under our editorial principles. Editorial Standards · Tips & Contact
Comments 0